> References > Heydar Aliyev International Airport Baku
- Location: Azerbaijan
- Solution: Airports
- Systems: Fire Alarm System
The project to renovate Heydar Aliyev International Airport, formerly known as Bina International Airport, started at the beginning of 1998 and was completed in June 1999.
The building comprises four modules, which operate as two terminals (north and south). One of the terminals is used for domestic and CIS passengers and cargo, and the other terminal is used for international passengers and cargo.
The design and project management work was carried out by British company APM Ltd and the building and civil works for the project by the Turkish consortium, Burc/Enka.
IATA CODE: GYD
| Commencement Date: | Mar-98 |
| Completion Date: | Jun-99 |
| Facts & Figures | |
| Terminal Design Capacity: (passengers per year) | 8,000,000 |
| Terminal Building Area: | 12,000m2 |
| Remote Boarding Gates: | 12 |
| Total Construction Period: (months) | 20 |